Active Projects
1200 Park Ave — Residential Units (Floors 3–8)
Skyline Build Co.
Active
1200 Park Ave — BOH & Common Areas
Skyline Build Co.
Active
88 Meridian St — Penthouse Fit-Out
Skyline Build Co.
On Hold
Phase Progress — 1200 Park Ave Residential
| Floor / Unit | Phase 1 · Rough-In | Phase 2 · Service | Phase 3 · Trim | Phase 4 · Closeout |
|---|---|---|---|---|
| 3rd Floor — Unit 3A | Done | Done | In Progress | — |
| 3rd Floor — Unit 3B | Done | Done | Stuck | — |
| 3rd Floor — Unit 3C | Done | In Progress | — | — |
| 4th Floor — Unit 4A | Done | Ready | — | — |
| 4th Floor — Unit 4B | In Progress | — | — | — |
| 5th Floor — Unit 5A | Stuck | — | — | — |
Critical Blockers
Unit 3B — Trim Phase Stuck
GC has not completed drywall in bathroom. Electrical trim cannot proceed until walls are closed. Waiting on GC foreman confirmation of completion date.
Unit 5A — Rough-In Stuck
Panel location change requested by architect. Awaiting revised drawings before conduit rough-in can continue. RFI submitted.
Recent Site Visits
SVR-260502-1200ParkAve — 3 issues logged, materials ordered
May 2, 2026
SVR-260429-1200ParkAve — GC coordination, no blockers
Apr 29, 2026
SVR-260425-1200ParkAve — Phase 2 progress, 2 units completed
Apr 25, 2026